How a Global Equipment Manufacturer Tamed Oversized Freight and Hit 95.3% On-Time Delivery

Case Study / August 12, 2026

Oversized freight does not forgive mistakes. When a load needs a step deck, a lowboy, or a state permit just to get on the road, a missed pickup is not an inconvenience. It is a stalled installation crew, an idle crane, and a project timeline slipping by the day.

That was the shipping reality for one of our newer customers: a global manufacturer of industrial technology systems, with North American operations based in the Midwest. Their equipment, including large fabricated components built for industrial plants, rarely fits neatly on a standard dry van. Here is how MyFreightWorld became their freight partner across truckload, LTL, and specialized oversized moves, and what the first five months of results looked like.

A global industrial equipment manufacturer moved 129 truckload, LTL, and oversized shipments with MyFreightWorld from February through June 2026, hitting 95.3 percent overall on-time delivery (97.6 percent truckload) while monthly volume nearly tripled.


The Snapshot

  • Industry: industrial equipment manufacturing 
  • Freight profile: mixed truckload, LTL, and oversized/specialized flatbed freight
  • Scope: 129 shipments managed February through June 2026
  • Headline result: 95.3% overall on-time delivery, with truckload at 97.6%

The Challenge: Freight That Does Not Fit in a Box

Most freight programs are built around standard equipment. This manufacturer needed the opposite. A single project could generate:

  • Oversized and overweight components requiring permits and route planning
  • Specialized equipment sourcing: flatbeds, step decks, hotshots, double drops, lowboys, and RGNs
  • Standard truckload and LTL shipments moving alongside the specialized freight
  • Vendor and off-load pickups coordinated with parties outside their own facilities
  • Tight scheduling windows tied to installation crews waiting at job sites

Freight moved from multiple production and staging locations to job sites and plants across the Midwest, Southeast, and Mid-Atlantic. Every lane brought its own mix of equipment needs, loading specifications, and scheduling pressure. Managing that through a patchwork of carriers and brokers meant inconsistent communication, uncertain capacity for the hard-to-cover specialized loads, and no single view of performance.

The Solution: One Partner Across Every Mode

MyFreightWorld took on the full freight profile rather than cherry-picking the easy loads. That meant:

A dedicated account team. A single account executive owns the relationship, backed by a sales manager and a director of capacity. When a load needs an RGN in three days, the customer makes one call, not ten.

Specialized capacity sourcing. Our capacity team vets and schedules carriers for oversized and permitted loads, matching each component to the right trailer type and handling the compliance details that come with OD freight.

Loading specifications on file. Shared spec sheets for large oversized components mean carriers arrive knowing exactly what they are picking up and how it loads, cutting down on dock-side surprises and detention.

Structured communication. Defined processes for issue resolution, vendor pickup coordination, and shipment updates, plus regular business reviews where performance is reported shipment by shipment.

A Quick Guide to Specialized Trailers

Covering this freight profile means matching every component to the right equipment. Here is the short version of what each trailer type does:

Trailer type When you need it
Flatbed Open deck for freight up to 8.5 ft tall loaded by crane or forklift
Step deck Lower rear deck adds clearance for loads over 8.5 ft tall
Hotshot Smaller expedited flatbed for urgent, lighter loads
Double drop Center well carries tall freight up to about 11.5 ft
Lowboy Rides inches off the ground for heavy equipment and machinery
RGN Detachable gooseneck lets wheeled machinery drive on and off
Specialized trailer guide comparing flatbed, step deck, hotshot, double drop, lowboy, and RGN

The Results: Five Months In

From February through June 2026, MyFreightWorld managed 129 shipments for the manufacturer: 85 truckload and 44 LTL, including the oversized and specialized moves.

Metric Result
Total shipments 129 managed across truckload, LTL, and specialized moves
Overall on-time delivery 95.3% (123 of 129 shipments)
Truckload on-time 97.6% (83 of 85)
LTL on-time 90.9% (40 of 44)
Volume growth 42 loads in month five, nearly 3x the starting volume
Freight program results table showing 95.3 percent on-time delivery across 129 shipments

That last number is the one we watch closest. Nobody triples their freight volume with a partner out of obligation. The growth came lane by lane, as covered loads and clean communication earned the next tender.

Specialized freight

Need flatbeds, step decks, or permitted oversized capacity? Tell us what you are moving.

Get a Quote

Frequently Asked Questions

What counts as an oversized load?

In most states, a load is oversized when it exceeds 8.5 feet wide, 13.5 to 14.5 feet tall (varies by state), or standard legal length or weight limits. Oversized loads typically require state permits, and the largest may need escort vehicles and approved routing.

What equipment do oversized loads require?

It depends on the dimensions. Freight under 8.5 feet tall can ride a standard flatbed. Taller components move on step decks or double drops, and heavy machinery typically requires a lowboy or RGN. The trailer guide above covers the common options.

How far in advance should specialized freight be scheduled?

More lead time is always better for specialized equipment. Permitted loads in particular need time for state permits and route planning. As a working rule, give your freight partner several business days for OD moves, though established programs with shared loading specs can often move faster.

How is on-time delivery calculated?

We count a shipment on time when it delivers by the scheduled delivery date. The figures in this case study cover every shipment in the program, including the hardest specialized moves, not a filtered subset.


Why It Works

Oversized and specialized freight rewards preparation. The wins in this program did not come from a magic rate. They came from spec sheets shared before pickup, carriers scheduled with enough lead time to do it right, and a team that treats a hotshot load with the same discipline as a full RGN move. Reliability compounds: every on-time delivery made the next project easier to plan.